Sc5080
Looks like a good start on your shop. Also looks like a nice size.
Most of the fill is in. Lots of fill ... way more than I expected. Almost 160 yards so far! And it will take a bunch more to tie in to the driveway. Should be starting on rebar tomorrow.
![]()
![]()
Also, I ordered the roof trusses today. Was told they would take four to five weeks now ... would have been one or two in the spring.![]()
Also, I ordered the roof trusses today. Was told they would take four to five weeks now ... would have been one or two in the spring.![]()
You and snopro need an "Indian Summer."
.
Working on my dream shop right now. Can't wait to have a roof.
Trusses are four weeks out.
Looks great.
Yours looks like its coming along nicely. [cl I'll be starting on the walls early in October. My trusses are due to arrive on the 16th or 17th. It will be all closed in before the end of October.